Most sewer line replacements take one to three days. Trenchless lining or bursting can finish in a day or two. Open-trench replacement, especially with permits, inspections, and concrete restoration, runs toward the longer end.

Typical Timelines

  • Pipe lining (CIPP) — one to two days including cure time
  • Pipe bursting — one to two days, plus access pit excavation and backfill
  • Open-trench replacement — two to four days depending on length and depth
  • Add time for permit and inspection scheduling, and for restoring concrete, asphalt, or landscaping

What Extends It

Depth and length. Deep laterals require more excavation and shoring. Long runs to the city connection scale proportionally.

Obstacles. Concrete driveways, mature trees, retaining walls, and crossing utilities all add complexity — and are precisely where trenchless methods earn their keep.

Permits and inspections. Requirements vary by jurisdiction, and inspection scheduling is not always same-day.

Restoration. Concrete cutting and repouring adds days, and cure time cannot be rushed.

Surprises. Occasionally a line is worse than the initial inspection indicated, which changes scope. Good camera work up front minimizes this considerably.

Living in the House Meanwhile

The practical question. Water service is usually available for most of the job, with specific windows where drains cannot be used. We tell you day by day what to expect rather than leaving you to guess, and where possible we plan those windows around your schedule. On longer jobs, temporary arrangements can sometimes be made.

Why Diagnosis Sets the Schedule

A camera inspection with locating tells us exactly what needs replacing and where, which is what makes an accurate timeline possible in the first place. Exploratory work takes longer and costs more — that is the real argument for scoping before digging.